ElectroDesigner — Engineering Software
Cable sizing workflow

Cable Sizing vs Ampacity: What Are You Actually Checking?

Cable design guide · Reviewed 22 Sep 2026 · ElectroDesigner

Ampacity is an input to cable sizing, not a synonym for cable sizing. Ampacity answers a thermal steady-state question: how much current can this conductor carry under defined installation conditions without exceeding its permitted temperature? Cable sizing adds several other constraints, including protective-device coordination, voltage drop, short-circuit thermal withstand, minimum cross-section rules and project-specific conditions.

1. Cable sizing and ampacity are different checks

For an IEC-style low-voltage workflow, start with the circuit design current Ib. Select a protective device with rated current In, then verify that the cable's corrected current-carrying capacity Iz is adequate for the actual installation. The familiar screening relationship is:

Ib ≤ In ≤ Iz

That relationship is essential, but it does not prove that the cable is fully sized. A conductor can pass the ampacity/protection check and still fail because the run is too long for the voltage-drop target, because the available fault energy exceeds its short-circuit thermal withstand, or because a minimum cross-section or special installation rule governs.

Key distinction: ampacity is a continuous-current thermal limit under stated conditions. Cable sizing is the design decision obtained after all applicable constraints are compared.

2. Core equations behind the workflow

A reference current-carrying capacity is corrected for real installation conditions using the factors applicable to the adopted standard or manufacturer data:

Iz = Iz,ref × ktemperature × kgrouping × kinstallation × …

For a preliminary AC voltage-drop check:

3φ: ΔU = √3 × I × L × (R cosφ + X sinφ)

For the adiabatic short-circuit thermal check:

I²t ≤ k²S²

The final conductor is therefore the smallest standard size that passes every active criterion, not merely the one whose table ampacity exceeds the load current.

3. Worked example: why “Iz > Ib” is not enough

Assume a feeder has:

Iz = 63 × 0.91 × 0.80 = 45.86 A

The cable can carry the 42 A design current under these assumptions, but the coordination check fails because:

42 A ≤ 50 A ≤ 45.86 A   →   false

If the 50 A protective device is to remain, the minimum required reference ampacity under the same two factors is:

Iz,ref,min = 50 / (0.91 × 0.80) = 68.68 A

The designer must therefore move to a candidate whose verified reference ampacity is at least 68.68 A under the relevant table/manufacturer basis, then still check voltage drop and short-circuit withstand. This example also shows why applying derating after selecting a cable can invalidate what initially looked like a comfortable choice.

4. Practical cable-selection workflow

  1. Determine Ib from the actual load model, including duty and applicable demand assumptions.
  2. Select the protective-device concept and candidate In.
  3. Classify the real installation/reference method.
  4. Obtain Iz,ref from the adopted standard or verified manufacturer data.
  5. Apply only the correction factors that belong to that rating basis.
  6. Check Ib ≤ In ≤ Iz and any additional overload requirements.
  7. Check voltage drop at normal operating conditions.
  8. Check short-circuit thermal withstand against prospective current/clearing time or verified total-clearing I²t.
  9. Check minimum cross-section, neutral/harmonics, mechanical and project-specific requirements.
  10. Select the largest minimum section required by all active criteria.

Run the IEC Cable Sizing Calculator

5. Assumptions and limits

Adjacent checks

Use the Cable Ampacity Calculator when you already have a verified base rating and want to inspect derating explicitly. Use the Voltage Drop Calculator for a deeper R/X-based drop check, and continue with the cable short-circuit thermal-withstand guide for the I²t constraint.

Engineering references

Current wiring-system reference: IEC 60364-5-52:2009+AMD1:2024 consolidated version. Practical method reference: Electrical Installation Guide — conductor sizing methodology.

Keep the cable checks connected.

A cable size is only complete when ampacity, installation conditions, voltage drop, protection and short-circuit thermal withstand have all been checked on the same design basis.